Agenda:
1. Status of the Project
2. Things TODO and schedule
3. Next meeting
Minutes:
1. Status of the project
Add list box widget (Nov 22) Team 2CompletedModify Image Label widget (Nov 22) Team 4CompletedFixed Timer widget (Nov 22) Team 4Completed- Save (Nov 17 - Nov 21) Team 1 In Progress
- Load (Nov 17 - Nov 24) Team 1 & Team 3 In Progress
Tasks assigned today after meeting:
- Team 1 - save functionality
- Team 3 - Load functionality
- Piping (Team 4)
- Escape / delete (Done small bug to be fixed)
- Tool tips (Priority 1)
- To delete the current pipe action (Priority 2)
- Team 2
- select and delete pipe
- show pipe when a new pipe is created between event and setproperty
- rename application
TODO:
- drag drop shadow
- export runnable jar (once save is done)
- Description of the pipe action
- Copy and paste pipe along with widget
- Pipe line
- Change to use java draw line
- Only focus on line if line selected
- Select volunteers for final presentation
- Preparation of presentation (Dec 9)
6. Next meeting will be held at Nov 23, 2009 after class